FleetClick
GA Fleet
Case Studies

Contractor Case Studies

TekWorx Optimization Control Makes the Most of Condensing Boiler Plant Design of NYC High-Rise

School District Boiler Retrofit

Boiler Plant Efficiency Improvement for Housing Complex

Award-Winning New Laboratory Project

Piping Freeze Protection for Cooling Tower

Rugged Snow-Melting Solution for Truck Ramp

Buddhist Temple Maintains Comfort with Floorwarming System


TekWorx Optimization Control Makes the Most of Condensing Boiler Plant Design of NYC High-Rise

A TekWorx Control & Energy Optimization (CEO) System does the thinking for the unique heating and domestic hot water system designed for a building completed in 2005.

Click here to read more.

Back to Top


School District Boiler Retrofit



For this performance contract retrofit project, GA Fleet helped a Long Island, NY school district update 11 schools with 41 AERCO boilers.

AERCO boilers provide heat during 95% of the heating season. Peak load is augmented with cast-iron dual-fuel boilers. An energy management system controls boiler firing rate for maximum system efficiency. Hot water temperatures are reset from 180 to 100 degrees for maximum efficiency; hot water pumps operate on VFDs to vary flow in response to changes in building load. AERCO boilers operate properly without primary pumps, isolation valves, or other flow.

Project Update: 2006
Since the original contract work was completed in 1997, the school district has built a 200,000 sq ft middle school and a 350,000 sq ft high school. In both of these schools the newer, larger AERCO BMK-2.0 boilers were specified by the school district, and are used year round for both heat and domestic hot water.


Beyond the high efficiency provided by the AERCO boilers, the school district takes advantage of an Interruptible Gas rate, further reducing their fuel costs. In this case the alternate fuel is Propane-Air, an all-gas alternate fuel solution that allows the use of high efficiency gas-fired equipment, rather than lower efficiency oil-fired equipment. The propane air system consists of a buried propane tank, with a vaporizer mixer (shown) and fully automatic controls and safety features.


The propane air system was supplied by GA Fleet and is fully integrated into the district's EMS system.

Back to Top


Boiler Plant Efficiency Improvement for Housing Complex


Boiler room shown before and after.

This 50-acre Queens, NY housing complex called for the retrofit of 11 circa 1950 #6 oil-fired firetube boiler rooms with 60 high-efficiency gas fired boilers. Each boiler plant provides heat and domestic hot water to several garden apartment buildings. An energy cost study completed by the consulting engineer indicated a 250% improvement in overall boiler plant efficiency.

Back to Top


Award-Winning New Laboratory Project



This project in a newly constructed laboratory building uses a 2,000,000 BTUH boiler plant to provide low temperature heating water. Boiler controls communicate with Johnson Controls BMS to vary HW reset temperatures from 130 to 80 degrees for maximum efficiency. This project won the Governors Award for design.

Back to Top


Piping Freeze Protection for Cooling Tower

This downtown NYC financial district building requires year-round cooling tower operation. A sophisticated powerline-based monitor and control system was selected by the consulting engineer to be the most cost-effective method to protect the piping from freezing and to monitor the pipe temperatures. Forty-five remote temperature transmitters are located at every pipe location that could contain standing (non-circulating) water, based on valve positions or pump operation. All monitoring is performed without any wiring, other than power to the heater cables.



Mission critical 24/7 cooling in this financial district building requires operating cooling towers and external water piping as large as 24" in the winter. Any pipe or valve freeze-up (and burst) would be catastrophic, so a fully-supervised system of monitoring and controlling heat tracing was specified.



Distributed pipe temperature sensing was determined to be the most accurate method of verification that pipes were not in danger of freezing. A patented powerline-based heat trace monitor and control system was determined the most cost effective method of providing distributed pipe temperature monitoring. Sensors were placed in the worst-case locations, namely between each isolation valve and the corresponding pipe connections to the cooling towers. Based on valve position and pump operation, these remote locations could contain non-circulating water, which is most likely to freeze.



Remote temperature sensors (the black junction boxes) are fully addressable, self-diagnostic, and "ruggedized" for industrial, transit, and low temperature/high vibrtion installations.



A modular control and monitor panel is provided to monitor the 5000 feet of heater cable and 45 temperature sensors. The spread-spectrum powerline communication technology utilized does not require filters or isolation transmitters, making it ideal for existing and retrofit applications. The only wiring required for this system is the power feed to the heater cables. All monitoring occurs over these wires.

Back to Top


Rugged Snow-Melting Solution for Truck Ramp

The most rugged, flexible, cut-to-length heater cables were selected for this industrial facility truck ramp. The ability to withstand vibration from commercial trucks, salt and other corrosive chemicals, and thermal expansion of the ramp assures heater cable life that will exceed that of the concrete ramp.



Cables are easily attached directly to rebar. A 2-stage pour is not required. Cable reels of 1000 feet each are provided and cut to length in the field. Field conditions often require modifications in cable lengths and layout from the original engineering design.



Heater cable power connections and terminations are above grade in accessible junction boxes. Only the rugged polyolefin jacket of the cable is in the slab. Rakes, shovels, and stone will not damage the heater cable. There are no buried splices that can fail due to poor manufacturing, handling, or galvanic corrosion.

Back to Top


Buddhist Temple Maintains Comfort with Floorwarming System

This Buddhist temple utilized over 11,000 feet of floorwarming cable to maintain carpet surface temperatures of 80 degrees for the comfort of its members. Finite element heat transfer models were generated by Raychem to design the floorwarming system with as little heater cable as possible. First floor heater cables were imbedded in the floor slab, second floor heater cables were located on the underside of the second floor slab.



Cables are installed prior to topping concrete pour. Cable reels of 1000 feet each are provided and cut to length in the field. Field conditions often require modifications in cable lengths and layout from engineering design.



Heater cable power connections and terminations are above grade in accessible junction boxes. Only the rugged polyolefin jacket of the cable is in the slab. There are no buried splices that can fail due to poor manufacturing, handling, or galvanic corrosion.



Custom made floor temperature sensing thermostats provide an additional level of control for comfort and energy savings. Capillary tubing of up to 50 foot lengths allow temperatures to be monitored in the center of the room(s). Installation in thermally conductive fluid-filled conduit provides rapid response and the ability for removal for future service.

Back to Top

CASE STUDIES BY PROFESSION

CASE STUDIES BY PRODUCT TYPE